1. Phase of efforts of preparation for the investor in the SSH project – specification of activites:

     - providing geodetic data, measurement of the construction
     - measurement of the locality, planimetry of the placement of the building and of the water gate
     - measurements in the river flow - sectioning of the water chanel and of the coastal band
     - measurement of the whole construction, alternate solutions
     - measurement of the coastal areas in the place of construction
     - geological data analyse, basic research of the target area
     - engineering and geological data, minimal research of the given area
     - expertise on envrinmental impacts of the project as required by law 127/1994

2. Phase - Engineering activities guiding the investor & his decision, leading to project documentation:

     - the whole concept for the investment decision
     - draft for the electrotechnical, machinery and electropart of the SSH, output, power
     - technical solution for the construction phase, placement in terrain,
     - adjustments of the solution to the actual state of the area, alternative solutions
     - technology type, assesment of the alternate solutions
     - concept for the construction part & electrical part, alternatives
     - subcontractors and their involvement in the solution
     - technical optimization of the subcontractors offers
     - cost estimate & calculation
     - economic optimization, assesment of the alternate solutions
     - economic concept of the SSH, costs, interest payments, taxes,
      calculated profit – ajdusting the economic concept of the SSH to the loan, energy prices
      and price growth per annum - alternative solutions for the investor
     - creation of a document describing all aspects of the project for the investment decision


The list of actions & services can be modified, most of these are required for the next step in the project documentation

3. Phase - project preparation & surrounding activities:

     - project documentation required for the territorial decision ( ÚR )
     - project documentation required for the construction permission ( SP )
     - hearing with the parties involved regarding these two legislative steps
     - all additional activities leading to succesfull granting of both required steps